Background. -- Air Force's February 2015 cost estimate for the JIAC military construction project did not fully meet best practices. -- DOD conducted multiple reviews of Lajes Field as a possible JIAC location. -- Conclusions. -- Recommendations for executive action. -- Agency comments and our evaluation. -- Appendices. |
Summary |
DOD's JIAC, which provides critical intelligence support for the U.S. European and Africa Commands and U.S. allies, is currently located in what DOD has described as inadequate and inefficient facilities at RAF Molesworth in the United Kingdom. To address costly sustainment challenges and instances of degraded theater intelligence capabilities associated with the current JIAC facilities, the Air Force plans to spend almost $240 million to consolidate and relocate the JIAC at RAF Croughton in the United Kingdom. GAO was asked to review analysis associated with consolidating and relocating the JIAC. This report (1) assesses the extent to which DOD's cost estimate for the JIAC consolidation at RAF Croughton aligns with best practices and (2) describes key reviews DOD has conducted since spring of 2013 related to an alternative location for JIAC consolidation. GAO recommends that DOD update its future construction cost estimates for consolidating the JIAC at RAF Croughton to comply with best practices for cost estimating identified by GAO. |
Note |
Online resource; title from PDF cover page (GAO, viewed December 7, 2016). |
Subject |
United States. Department of Defense -- Rules and practice -- Evaluation.
|
|
Military bases, American -- Great Britain -- Costs.
|
|
United States -- Armed Forces -- Military construction operations -- Decision making -- Evaluation.
|
Genre/Form |
Online resources.
|
|
Electronic books.
|
|
Electronic government information.
|
Added Author |
Lepore, Brian J.
|
Added Title |
Joint Intelligence Analysis Complex, Department of Defense needs to fully incorporate best practices into future cost estimates : report to congressional requesters |
|
DOD needs to fully incorporate best practices into future cost estimates |
Running Title |
GAO-17-29, Joint Intelligence Analysis Complex |
Gpo Item No. |
0546-D (online) |
Sudoc No. |
GA 1.13:GAO-17-29 |
|